11kV Substation Installation
11kV Substation Installation
Industry Sector: Government Laboratory
Background
11kV Substation Installation – The client required a new HV electrical supply to a number of small buildings and the HV electrical supply also required upgrading. The design called for a new 11kV substation to be installed in a remote part of the site.
Project Duration
8 Weeks
Technical Remit
- Design.
- Supplied and installed a ring main unit & transformer combination.
- Carried out civil works and installed a new concrete base, complete with security fencing.
- 3 Phase HV cable installation – required a trench through a forest, which crossed roads and footpaths, train tracks and many underground obstacles on the client’s estate.
- Connection of the new substation to the point of connection.
- Completed joints and terminations.
- Test and commissioning.
Outcome
Successful Installation. Project delivered on time, to plan and in budget.